gold ore crusher is one of the high fine crushing equipment widely used in industrial production in South Africa, mainly by feeding part, discharging part, turning part, transmission and other components. Hollow shaft with steel, lined with removable, rotary gear hobbing by casting, the body inlaid cylinder liner wear, has good abrasion resistance. The machine running smoothly, reliable performance, widely used in mineral processing, building materials and chemical industry. According to the materials and methods of discharge, optional dry and wet lattice-type gold crusher.

Preparing For Gold Ore Crusher Installation

Whether the installation is a large gold crusher, a small gold crusher or medium-sized gold crusher installed in the mill manufacturers have the technical staff to guide the installation.

  1. 1. in the former gold ore crusher South Africa installation, you must remove the anti-rust oil on all parts machined surfaces, guards and dust and dirt falling behind in the transport of.
  2. 2. when the gold crusher is installed, the contact surface between the parts should be lubricated, fixed surface with a dry oil lubrication, surface activity with oil lubrication.

Gold Crusher Bearing Mounting Portion

  1. 1. the gold crusher South Africa must be fed by a main bearing cap is installed nominal size slightly outward shift some of the cylinder in order to meet the needs of elongation due to heat.
  2. 2. dust and clean the gold crusher to get the net bearings and friction surfaces carefully sump with kerosene.
  3. 3. the ball will be given by the cooling water circulation pipe joint assembly.

Gold Ore Crusher Liner Installation

  1. 1. gold crusher liner installation shall be cleaned of grease inside the cylinder.
  2. 2. gold crusher South Africa during installation should ensure that the gap is not more than 16mm, fixed liner spiral pad should carefully packing and sealing gaskets to prevent leakage of slag, such as when no gasket should be wrapped around two in the corresponding position circle of cotton or hemp cord leaded oil. Should be installed in the cylinder wall plaster layer (1:2) cement mortar, before solidification screw tightened.

Hot Sale

Maybe You're Interested

Clay Sand Raymond Mill

The Use Of Calcined Petroleum Coke Powder

Potassium Feldspar Uses And Processing Production

Fly Ash Classification Machine Suppliers

Limestone Grinding By SCM1000 Ultrafine Roller Mill, For 1250 Mesh Plastic Industry